Building a Straw Bale Meditation Space
Tuesday, 27 November 2012
Work inside
Pumpkin
Limecrete floor on east wing
JCB mixing Clay, Sand and Straw for the floor and walls
First layer of earth floor going down
Lime wall and stud work
<
Alan and Tom brushing on the first coat of clay with a broom!
Sarah painting clay onto the reed matting
Second coat of clay going on the walls
Wind and rain damage, i think i'll keep the swimming pool
More clay plastering
/a>
Thursday, 25 October 2012
I've finished!... the outside...almost.
Started work on the floor. Thats recycled foam glass for the insluation layer, not coal, if you were wondering.
Mixing shelter
2nd coat of lime
Smooth, top coat of lime
All done
Friday, 5 October 2012
Hello autumn
Roof light windows, planed, lead flashing, watertight
Shingles, tapers cut and nailed
Cut a hole in the roof, installed flue.
Cover finaly off, no leaks in the roof.
Lime plaster outside walls, coat number one, scratch coat.
>
Saturday, 28 July 2012
Finally finished the batters and now started putting the shingles on.
Monday, 11 June 2012
June
Thursday, 26 April 2012
Rafters
Im working on the rafters at the moment, I just ordered 680 meters of batten and 4600 Cedar shingles,that should keep be busy for a while!
Saturday, 24 March 2012
Straw!